Complete the table; find average lateness, average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D)
Job Process Time Flow Time Due Date Lateness
A 5 7
B 3 9
C 2 12
D 5 4
Sum (Average) 15 (3.75 ) XXXXX
Job Process Time Flow Time Due Date Lateness
A 5 5 7 0
B 3 8 9 0
C 2 10 12 0
D 5 15 4 11
Sum (Average) 15 (3.75 ) 38 (9.5 ) XXXXX 11 (2.75 )
Avg lateness = 11/4 = 2.75 days
Avg completion time = 38/4 = 9.5 days
Avg number of jobs in the system = 38/15 = 2.53 jobs
You might also like to view...
Which of the following specific measures of vendor quality would be used when evaluating vendors that supply a company with direct materials?
a. Defect-free material as a percentage of total materials received b. Number of customer complaints c. Time it takes to make a product d. All would be considered to assess vendor quality of direct materials.
Plant life is not considered to be real property.
Answer the following statement true (T) or false (F)
It is important to keep in touch with a customer and make a sales pitch each time.
Answer the following statement true (T) or false (F)
Pools of money invested in a portfolio that is fixed for the life of the fund are called
A. closed-end funds. B. open-end funds. C. unit investment trusts. D. REITS. E. redeemable trust certificates.