If the standard deviation is 3.4, the Z value is 1.95, and the expected date of completion is 38 months, then the due date for project completion is ______.
a. 44.63 months
b. 62.78 months
c. 32.55 months
d. 24.50 months
a. 44.63 months
You might also like to view...
The three forms of business entities are:
a. Government, cooperatives, and philanthropic organizations b. Financing, investing, and operating c. Sole proprietorships, partnerships, and corporations d. Wholesaler, manufacturer, and retailer
The term _______________ is defined by the Merriam-Webster dictionary as “a firm adherence to a code of especially moral or artistic values.”
a. Reciprocity b. Accountability c. Integrity d. Commitment
How should a paralegal respond when a potential client asks in an initial interview, "Do I have a winning case?"
A) Answer by stating, "Yes." B) Answer by stating, "I doubt it." C) Answer by stating, "I think so." D) Answer by stating, "The attorney will discuss that with you."
Native advertising and content marketing are the same thing.
Answer the following statement true (T) or false (F)