A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300

What is the highest total cost for completing this project?

Activity Normal time Crash time Normal Cost Crash Cost Predecessor
A 8 5 $1,000 2,000
B 6 4 1,500 2,000 A
C 8 5 1,800 2,300 A
D 12 9 1,000 1,800 B
E 14 11 950 1,450 B
F 9 7 1,500 1,900 C, D
G 7 5 2,300 2,800 E, F
A) $14,250
B) $13,950
C) $13,550
D) $13,150


A

Business

You might also like to view...

What are three significant cost drivers that have been disregarded by traditional product costing system?

Business

The 12-month period that ends when a company's sales activities are at their lowest level is called the:

A. Interim period. B. Natural business year. C. Fiscal year. D. Accounting period. E. Calendar year.

Business

The price associated with a resource that indicates how much more profit would be earned by increasing the amount of the resource by one unit is called ______.

a. final cost b. reduced cost c. shadow price d. single price

Business

Violations of environmental laws are civil violations; there are no criminal penalties that can result in prison time

a. True b. False Indicate whether the statement is true or false

Business