A project has been established in a large online retailer to develop a new secure online retail platform. During the development, you discover that a key piece of software used as part of the base platform is now susceptible to recently published exploits. Who should be contacted FIRST by the project team to discuss potential changes to the platform requirements?
A. stakeholders
B. project sponsor
C. upper management
D. change control board
D
Explanation: The change control board should be contacted first to discuss the potential changes to the platform requirements. The change control board should always be contacted first when a change must be made to the project.
Next, you should contact the project stakeholders. After that, you can notify the project sponsor and upper management.
You might also like to view...
To delete an incorrect character in a document, simply click next to the incorrect character and then press the ____ key(s) to erase to the left of the insertion point.
A. COMMAND-HOME B. DELETE C. FN-DELETE D. END
Identify aproject type that generates substantial new revenue or profits for the firm.
a. Breakthrough b. Enhancement c. Maintenance d. Growth
To combine two or more cells in a Quick Table, you click the ________ Cells button
A) Unite B) Meld C) Join D) Merge
When assigning a command button to a macro, by default the button displays on the DEVELOPER tab
Indicate whether the statement is true or false