If one resource is assigned to a task with a duration of 1 day, the total work would be ____.
A. 8 hours
B. 1/7 week
C. 1/30 month
D. Any of the above
Answer: A
You might also like to view...
What can you use for sources of data for mailing labels? Is there anything special you would do for mailing labels based on parameter queries?
What will be an ideal response?
What field in the basic IPv6 header is used to chain additional headers?
A. Chain Header B. Next Header C. Header PTR D. Extensions
A Web page link can be used when the information located on the Web is too lengthy to put into your notes
Indicate whether the statement is true or false
EXX Case 3-1Coach Wright is the coach of the varsity football team. In preparation for his next team meeeting, he wants to create some charts tracking the players weight, time spent in practice, and game performance. To restrict the data entered in certain cells, Coach Wright will click the _____ button in the Data Tools group on the Data tab.
A. Data Validation B. Consolidation C. What-If Analysis D. Advanced