Give an example of an option to delay a project. Why might this be of value?

What will be an ideal response?


There is no question that the estimated cash flows associated with a project can change over time. In fact, as a result of
changing expected cash flows, a project that currently has a negative net present value may have a positive net present
value in the future. The ability to delay this project with the hope that technological and market conditions will change,
making this project profitable, lends value to the project and it is called an option to delay. An example of the option to
delay a project until the future cash flows are more favorable could be a firm that owns the oil rights to some oil-rich
land and is considering an oil-drilling project. Suppose that after all of the costs and the expected oil output are
considered, the project has a negative net present value. Does that mean the firm should give away its oil rights or that
those oil rights have no value? Certainly not. There is a chance that in the future oil prices could rise to the point that
this negative NPV project could become a positive NPV project. It is this ability to delay development that provides
value. Thus, the value in this seemingly negative NPV project is provided by the option to delay it until the future cash
flows are more favorable.

Business

You might also like to view...

The initial owners of stock of a newly formed corporation are called directors

a. True b. False Indicate whether the statement is true or false

Business

Uncertainty that the party on the other side of an agreement will abide by the terms of the agreement is referred to as

a. credit risk. b. exchange rate risk. c. interest rate risk. d. price risk.

Business

Publicly held firms that apply U.S. GAAP or IFRS must show earnings per common share data in the body of the income statement

Indicate whether the statement is true or false

Business

Which of the following cost-reduction and process-improvement techniques is often used in conjunction with target costing?

A. Cost allocation. B. Value engineering. C. Deterministic simulations. D. Budgetary padding. E. Linear programming.

Business