On a practical basis a, manager should always accept all positive NPV projects even if this means exceeding a limited budget

Indicate whether the statement is true or false.


Answer: FALSE
Explanation: On a practical basis, a manager should accept the combination of positive NPV projects that maximizes the total NPV while still operating within budget.

Business

You might also like to view...

On February 3, Smart Company sold merchandise in the amount of $1800 to Truman Company, with credit terms of 1/10, n/30. The cost of the items sold is $1240. Smart uses the perpetual inventory system and the gross method. Truman pays the invoice on February 8, and takes the appropriate discount. The journal entry that Smart makes on February 8 is:

A.

Cash1720? 
Sales discounts12? 
Accounts receivable 1732.00?

B.
Cash1800? 
Accounts receivable 1800?

C.
Cash1782.00? 
Sales discounts18? 
Accounts receivable 1800?

D.
Cash1240? 
Accounts receivable 1240?

E.
Cash1160? 
Accounts receivable 1160?

Business

Which practical tool was created to analyze and interpret the four kinds of change conversations?

a. manager’s handbook b. discussion inventory c. conversational profile d. gap analysis

Business

In a bilateral contract, the offeree's promise is the acceptance

Indicate whether the statement is true or false

Business

The activity-based costing system

A) is the most appropriate method of cost accounting for rigid hierarchical organizations. B) effectively departmentalizes an organization based on its core functions, such as human resources and maintenance. C) provides a more accurate picture of how costs should be charged to products and services. D) assumes that organizations are bureaucratic "machines" that can be separated into component functions. E) fails to allocate costs across business processes and is less effective than traditional methods of cost accounting.

Business