What is a summary task, and how are summary tasks used for project scheduling?
What will be an ideal response?
A summary task is a task representing a general activity of construction, and
usually contains multiple subtasks. An example would be constructing a concrete slab,
which contains multiple subtasks such as initial layout, excavation, preparation of the
base, installation of rebars and other utilities, placement, finishing and curing of the
concrete. Summary tasks are used for project scheduling to provide an outline structure
to the schedule that identifies the project's major phases. Typically, no duration is
initially associated with summary tasks.
You might also like to view...
The most ethnically diverse region of colonial America was ____, whereas ____ was the least ethnically diverse.
A. New England, the South B. the middle colonies, the South C. the South, New England D. the middle colonies, New England E. the frontier regions, New England
Crowfoot wrenches are available in which design?
A) Open end B) Flare nut C) Both A and B D) Neither A nor B
A technician attaches one lead of a digital voltmeter to the ground terminal of the TP sensor and other meter lead to battery negative terminal. The ignition is turned on, engine off and the meter displays 37.3 mV
Technician A says that this is the signal voltage and is a little low. Technician B says that the TP sensor ground circuit has excessive resistance. Which technician is correct? A) Technician A only B) Technician B only C) Both technicians D) Neither technician
An effective time delay device can be constructed by using the propagation delay characteristics of a parallel shift register
Indicate whether the statement is true or false