Compressing activities on a project with a sensitive project network will:
A. Increase risk of delaying the project and reduce scheduling flexibility.
B. Improve cost-time crashing success.
C. Reduce scheduling flexibility.
D. Increase risk of delaying the project.
Answer: A
You might also like to view...
Which of the following statements regarding contingencies is true?
a. Contingencies that are probable and not estimable appear on the balance sheet. b. Contingencies that are probable and not estimable are disclosed in the notes to the financial statements. c. Contingencies that are remote but estimable are disclosed in the notes to the financial statements. d. Contingent assets are recorded on the balance sheet, but not in the notes to the financial statements.
Which of the following statements concerning activity-based costing is not true?
a. It assigns costs evenly to jobs using an overhead rate, even though different jobs actually consume resources in different proportions. b. As a result of implementing it, as many costs as possible can be specifically traced to the individual jobs. c. It is worthwhile to implement when different jobs use resources in different proportions. d. Costs that cannot be traced to individual jobs can be separated into homogeneous cost pools and then allocated to individual jobs.
A high self-esteem living space is one that
A) costs way more than the average living space in the area. B) has the latest technology, such as being a smart house. C) honors the person you are. D) requires low maintenance.
Use the information in Table J.5. The average past due using the ratio (CR) rule, is:
A) fewer than or equal to 9.0. B) greater than 9.0 but fewer than or equal to 18.0. C) greater than 18.0 but fewer than or equal to 27.0. D) greater than 27.0.