Which specifications are used for parts of the project that are difficult to verify for correctness after construction has been completed?

a. technical c. performance
b. design d. master format


A
technical

Trades & Technology

You might also like to view...

Which of the following is the symbol for an eductor?

A.
B.
C.
D.

Trades & Technology

The best way for crew leaders to encourage crew safety is to _____.

a. conduct regular workplace inspections b. create unsafe conditions to test workers c. set a good example for them d. promote good communication

Trades & Technology

A V-6 internal combustion engine burns fuel at the rate of 5.5 gallons per hour. The fuel has a heating value of 42.7 kJ/mL. Calculate the useful output to the power train (in kilowatts) if the overall efficiency is 35 percent.

What will be an ideal response?What will be an ideal response?

Trades & Technology

In a running engine with a CR diesel system, what force(s) hold the nozzle needle seated when the actuator is not energized?

A. hydraulic force only B. spring force only C. electrical force only D. combined spring and hydraulic force

Trades & Technology