A resident project representative should:

A. allocate areas for construction shacks for the sub-contractors.
B. set the starting and stopping times of the job.
C. supervise the activities of the inspection on the project.
D. keep tabs on the general contractor to insure that he or she is within the project budget.
E. supervise the construction work on the project.


C

Trades & Technology

You might also like to view...

Answer the following statements true (T) or false (F)

Tip layering is an illustration of reversal of polarity in rooting of a shoot.

Trades & Technology

The term _____ refers to growth resulting from an increase in the number of cells

a. Hyperplasia c. Meiosis b. Turgor d. Hypertrophy

Trades & Technology

Look up the numerical value for the following factors from the compound interest factor tables.

1. (F?P,10%,7) 2. (A?P,12%,10) 3. (P?G,15%,20) 4. (F?A,2%,50) 5. (P?G,35%,15) What will be an ideal response?

Trades & Technology

Termites tend to enrich soils in the tropics much the same way as earthworms do in temperate region soils

Indicate whether the statement is true or false

Trades & Technology