Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively, compute the PERT standard deviation for this activity
A) 2
B) 4
C) 5
D) 15
E) None of the above
A
You might also like to view...
Discuss the philosophy of win-win not yet negotiating in a negotiation session.
What will be an ideal response?
Checks returned by a bank because customers did not have sufficient funds in their account are called
a. Canceled checks b. Certified checks c. NSF checks d. Outstanding checks
An example of Nonaka’s (2001) tacit-explicit knowledge creation could be the organization codifying and writing up procedural and training manuals in order to train new employees. Nonaka refers to this process as ________________.
a. Socialization b. Internalization c. Articulation d. Combination
________ is a rule which provides that an action for breach of any written or oral sales or lease contract must commence within four years after the cause of action accrues
A) Perfect tender rule B) Specific performance decree C) Replevin D) Statute of limitations