In a Design/Bid/Build contractual arrangement, the architect signs a contract with the _________

a. Owner
b. Construction manager
c. General contractor
d. Subcontractor
e. None of the above


A

Trades & Technology

You might also like to view...

Technician A says each module in a CAN system receives every communication on the serial data bus. Technician B says only the messages with the correct heading are responded to by a module in a CAN system.

A. Technician A B. Technician B C. Both A and B D. Neither A nor B

Trades & Technology

What is the difference between an azeotropic mixture and a near-azeotropic mixture?

What will be an ideal response?

Trades & Technology

A parallel heat reclaim system primarily recovers:

A) Sensible heat from the refrigerant. B) Latent heat from the refrigerant. C) Both sensible and latent heat from the refrigerant.

Trades & Technology

How can hermetic compressors be characterized?

A) They have a welded shell with a shaft that connects to an external motor. B) They have a shaft that connects to an external motor. C) They have a welded shell, which holds both the compressor and motor. D) They have a bolted housing that encloses both the compressor and motor.

Trades & Technology