The ____ dialog box is useful when you want to track and update groups of tasks but don't need the detail you applied to tasks when you used the Update Tasks dialog box or the Gantt chart.

A. Update Project
B. Status Report
C. Tracking Report
D. Task Tracking


Answer: A

Computer Science & Information Technology

You might also like to view...

Which range of SQL Server error message severity levels are user-generated messages that must be fixed by the user?

A. 1-10 B. 11-16 C. 17-10 D. 20-25

Computer Science & Information Technology

What is a ‘wicked problem’. Explain why the development of a national medical records system should be considered as a ‘wicked problem’.

What will be an ideal response?

Computer Science & Information Technology

Remove all files from the backup directory

What will be an ideal response?

Computer Science & Information Technology

The shortest time to recovery method in the event of a complete datacenter failure is to utilize a:

A. warm site. B. hot site. C. cold site. D. private cloud. E. hybrid cloud.

Computer Science & Information Technology