Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?
A. Less work has been done than planned
B. The same amount of work has been done than planned
C. The project has cost less than planned
D. There is not enough information to draw a conclusion
E. More work has been done than planned
Answer: E
You might also like to view...
You can signal a change in direction within a paragraph by starting a new sentence to introduce an additional topic
Indicate whether the statement is true or false
Managerial Basic Training (Scenario)Imagine that your marketing company has just merged with a manufacturing organization. You have been asked to help provide some "basic" managerial training to the engineers in the research and development unit of the new company. To ensure you are covering the important issues, your boss has asked to see an overview of materials that you will be providing the engineers.The engineers have to be informed that, ________ are the people who direct the activities of others in an organization.
A. directors B. managers C. subordinates D. line workers
Manufacturers must use due care in selecting the materials to be used in a product
Indicate whether the statement is true or false
Among the three levels of compliance of the ODBC API standards, Level-1 provides support for procedural SQL and cursors
a. True b. False Indicate whether the statement is true or false