If a defect is known to the owner at the time of acceptance, and the owner did not object or reduce payment due the contractor or designer, has the owner waived any claim against the contractor or designer?
What will be an ideal response?
A court may find that the owner waived any claim, but no such assumption
should be made concerning hidden or latent defects. Moreover, standard
form documents explicitly reject equating acceptance of the project with
waiver of claims.
You might also like to view...
The process of coating a substrate with a plastics powder is sometimes called ____ painting.?
A. ?dry B. ?calendar C. ?extrusion D. ?transfer
Answer the following statement(s) true (T) or false (F)
The basic START–STOP push button control circuit discussed in Chapter 7 can be modified to include a second STOP and START push button.
When installing multi-family services, the service disconnect _____.
a. must always be placed outside b. must always be placed indoors c. may be placed indoors under specific circumstances d. must be inaccessible to tenants
The term ____________________ field development refers to development occurring on land previously used for factories where there is significant contamination of the soil with chemical toxicants
Fill in the blank(s) with correct word