Task C is directly preceded by two tasks–task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The EF for activity C is week
A) 7.
B) 14.
C) 12.
D) 24.
D) 24.
You might also like to view...
Accommodators believe that winning is most important
Indicate whether this statement is true or false.
Personnel are best adapted to local conditions through which method of classifying jobs?
a. geographic classification b. functional classification c. product classification d. interdivisional classification
A multisegment targeting strategy differs from a concentrated targeting strategy in that it:
a. selects one segment of a market with a goal to satisfy its members. b. faces a high potential cost from cannibalization of products. c. develops and maintains a common marketing mix for its products. d. results in sterile, unimaginative product offerings.
The Federal Tort Claims Act of 1946 requires the federal government to ________
A) file legal actions against corporations violating strict liability torts B) waive sovereign immunity for the tortious acts of its employees in certain cases C) measure the cost that a proposed rule would impose on a business D) hold every portion of a business meeting open to public attendance