The delivered equipment cost for setting up a production and assembly line for high-sensitivity, gas-damped accelerometers is $650,000. If the direct cost and indirect cost factors are 1.36 and 0.31, respectively, and both factors apply to delivered equipment cost, the total plant cost estimate is approximately: (choose one)
(a) $2,034,500
(b) $1,815,500
(c) $1,735,500
(d) $1,183,000
CT = (1 + 1.36 + 0.31)(650,000) = $1,735,500
Answer is (c) $1,735,500
You might also like to view...
A putty-like mixture of resin, catalysts, fillers, and short fiber reinforcements is known as ____.
A. ?short fiber compounds B. ?bulk molding compounds (BMC) C. ?reinforced thermoplastics (RTP) D. ?sheet molding compounds (SMC)
The carcass of an animal that has died from anthrax should be sold for tankage
Indicate whether the statement is true or false.
The walls of a structure make up a large portion of the ____________________ or shell of the structure.
Fill in the blank(s) with the appropriate word(s).
The infrared humidifier consists of a horizontal water reservoir and infrared lamps with _____
a. plates b. a sponge c. reflectors d. heaters