If a project is delayed due to design modifications what construction documentation could be used to prove it caused delays on a project?
What will be an ideal response?
The construction documentation that could be used to help prove a delay was caused by design modifications is the following:
a) The Schedule (S)
b) The Correspondence Log (COR)
c) The Change Order Log (COL)
d) The Request for Information Log (RFI)
e) Daily Construction Reports (DCR)
f) Progress Curves (PC)
g) The Drawing Log (DL)
You might also like to view...
A focal point is effective even if it does not fall within the viewer's immediate range of vision
Indicate whether the statement is true or false
____________________ soybean varieties have continual stem elongation throughout the growing season
Fill in the blank(s) with correct word
Acceptance sampling cannot be handled by statistical quality control (SQC) equations
Indicate whether the statement is true or false.
The left rail of a hand-wired relay ladder diagram is labeled __________.
A. L1 B. L2