If a project is delayed due to design modifications what construction documentation could be used to prove it caused delays on a project?

What will be an ideal response?


The construction documentation that could be used to help prove a delay was caused by design modifications is the following:

a) The Schedule (S)
b) The Correspondence Log (COR)
c) The Change Order Log (COL)
d) The Request for Information Log (RFI)
e) Daily Construction Reports (DCR)
f) Progress Curves (PC)
g) The Drawing Log (DL)

Trades & Technology

You might also like to view...

A focal point is effective even if it does not fall within the viewer's immediate range of vision

Indicate whether the statement is true or false

Trades & Technology

____________________ soybean varieties have continual stem elongation throughout the growing season

Fill in the blank(s) with correct word

Trades & Technology

Acceptance sampling cannot be handled by statistical quality control (SQC) equations

Indicate whether the statement is true or false.

Trades & Technology

The left rail of a hand-wired relay ladder diagram is labeled __________.

A. L1 B. L2

Trades & Technology