The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

Fill in the blank(s) with the appropriate word(s).


backward pass

The backward pass determines which activities represent the critical path. The critical path is the longest path in the network which, when delayed, will delay the project and determines how long the activity can be delayed without delaying the project.

Business

You might also like to view...

Holographic wills are oral wills declared by the testator in the presence of witnesses.?

Indicate whether the statement is true or false

Business

Compared to transactional leadership, transformational leadership is more aligned with organizational change required by total quality and Baldrige-like performance excellence models

a. True b. False Indicate whether the statement is true or false

Business

The Discount on Bonds Payable account is:

A. expensed only at the bond's maturity. B. a contra account to Bonds Payable. C. an expense account. D. a miscellaneous revenue account.

Business

It is normal for a company's strategy to end up being _______.

A. left unchanged from management's original planned set of actions and business approaches since making on-the-spot changes is too risky. B. a combination of defensive moves to protect the company's market share and offensive initiatives to set the company's product offering apart from rivals. C. like the strategies of other industry members since all companies are confronting much the same market conditions and competitive pressures. D. a blend of deliberate planned actions to improve the company's competitiveness and financial performance and as-needed unplanned reactions to unanticipated developments and fresh market conditions. E. a mirror image of its business model, so as to avoid impairing company profitability.

Business