If the standard deviation is 3.4, the Z value is 1.95, and the expected date of completion is 38 months, then the due date for project completion is ______.
A. 44.63 months
B. 62.78 months
C. 32.55 months
D. 24.50 months
A. 44.63 months
You might also like to view...
On November 1, 2018, A-1 Products borrowed $64,000 on a 5%, 5-year note with annual installment payments of $12,800 plus interest due on November 1 of each succeeding year. On November 1, 2020, what is the balance of the Long-Term Notes Payable account? (Round your answer to nearest whole number.)
A) $38,400 B) $64,000 C) $51,200 D) $12,800
In a neutrality agreement
A. both the employer and the employee agree to binding arbitration. B. the employer agrees not to campaign against or disparage the union. C. labor and management submit to organizer training. D. labor agrees to bring all grievances to a mediator.
How is an asset allocation fund different from a balanced mutual fund?
What will be an ideal response?
Control functions are located in routers in ________
A) traditional routing B) SDN C) both A and B D) neither A nor B