When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?
A. Physical
B. Resource
C. Technical
D. Time
E. All of these are types of constraints that could impact structure of the project network
Answer: D
You might also like to view...
In a statement of cash flows, which of the following events would be classified as a financing activity?
A) the purchase of a trading security B) the payment of interest on a loan C) the payment of cash dividends to shareholders D) all of these answer choices are correct
A numerical description of the outcome of an experiment is called a
A. descriptive statistic. B. probability function. C. variance. D. random variable.
Trump Company Other revenues $110,000 General and administrative expenses $250,000 Dividends $120,000 Gross profit $750,000 Selling expenses $220,000 Income tax expense $117,000 Refer to the information provided for Trump Company. What is Trump Company's income from operations?
A) $160,000 B) $280,000 C) $220,000 D) $120,000
In the public sector we should manage our own behavior and influence the behavior of others in a manner that is consistent with the public interest and the values of ________.
A) Consultative approach B) Democratic governance C) Leadership D) Capitalism