John, a civil engineer, pays the heavy equipment provider an agreed-upon hourly rate and unit price for the various materials to be used. In the context of contract categories, this scenario is an example of a:
a. cost-plus-fee contract.
b. cost-plus-percentage contract.
c. fixed-price contract.
d. time and material contract.
d. time and material contract.
In atime and material contract, the buyer pays the provider for both the time and materials required to complete the contract. The contract includes an agreed-upon hourly rate and unit price for the various materials to be used.
You might also like to view...
If you perform an incorrect action, clicking the ________ button will often return your document to its previous state
Fill in the blank(s) with correct word
A(n) ________ is an interactive computer terminal available for public use
Fill in the blank(s) with correct word
A(n) ____________________, is an act of sabotage that attempts to flood a network server or Web server with so many requests for action that it shuts down or simply can no longer handle requests, causing legitimate users to be denied service.
Fill in the blank(s) with the appropriate word(s).
Which of the following cable types designates that it can safely be run through a drop ceiling ?
A. STP B. Plenum C. CAT5e D. UTP