The 100% rule suggests that before a PERT chart is done, a project manager must:

A. Make sure that each person on the project team got 100% on their project management final exam.
B. Make sure 100% of the project tasks are defined.
C. Make sure 100% of the project is funded.
D. Make sure the project team is devoted solely or 100%, to this project.


Answer: B

Business

You might also like to view...

Leadership in which type of marketing system is assumed not through common ownership or contractual ties but through the size and power of a single dominant channel member?

A) a horizontal marketing system B) an administered vertical marketing system C) a corporate vertical marketing system D) a conventional marketing system E) a multiple distribution system

Business

Which of the following will help you track progress over time and help to ensure all deadlines are met?

A) An audience analysis B) A work plan C) An outline D) Predetermined research activities E) Identification of audience needs

Business

Marion Manufacturing had the following cash flows for the current year. The company uses the direct method in preparing the statement of cash flows. Cash receipts from issuance of stock$60,000 Bonds payable issued at face value 250,000 Cash dividends received from long-term investments 4,500 Cash paid for wages 20,000 Cash paid for dividends 5,000 Cash received from customers 42,500 Cash paid for other operating expenses 19,500 Cash paid to purchase equipment 100,000  What is the net cash provided by (used in) operating activities?

A. $3,000 B. ($37,500) C. $7,500 D. ($2,000)

Business

The Delphi method is particularly useful because it can avoid what problem?

a. Group think b. The voice of the customer c. Wisdom of crowds d. The Peter principle

Business