At Morgan's Transformer Rebuilding, a set of five jobs is ready for dispatching to a machine center. The processing times and due dates for the jobs are given in the table below

Use shortest processing time to sequence the jobs, and calculate the average completion time, the average job lateness, and the average number of jobs in the machine center.

Job Work Time (days) Due Date (days)
A 15 38
B 13 28
C 7 20
D 18 50
E 9 15


The optimal sequence is C-E-B-A-D. The average completion time is 31.6 days. The average lateness is 4 days. The average jobs in system is 2.548. Details appear in the table below.

SPT Time Due Date Slack Flow time Late days
C 7 20 13 7 0
E 9 15 6 16 1
B 13 28 15 29 1
A 15 38 23 44 6
D 18 50 32 62 12
Total 158 20
Average 31.6 4
Average number of jobs in system: 2.548

Business

You might also like to view...

________ collect scanner data wherein panel members are issued an ID card allowing panel members' purchases to be linked to their identities

A) Focus group panels B) Modular group panels C) Scanner panels D) Audit panels E) Cashier panels

Business

Qualitative information that a manager might evaluate in making a decision would include all of the following EXCEPT ________.

A) calculating the breakeven point under two different alternatives B) the effect of layoffs on employee morale C) the reduction in control over delivery time due to subcontracting D) upsetting regular customers by offering discounts to selected customers

Business

Operating income is gross profit minus operating expenses

Indicate whether the statement is true or false

Business

Developing strategies to close capacity gaps (where utilization of a resource exceeds capacity available) is most often accomplished by acquisition of more resources through expansion and new facility construction.

Answer the following statement true (T) or false (F)

Business