Pierceall Corporation is conducting a time-driven activity-based costing study in its Tech Support Department. The company has provided the following data to aid in that study:Activity Data:Routing CallsResolving ProblemsPreparing Change OrdersMinutes per unit of the activity162838?Cost Object Data:Customer JCustomer KCustomer LNumber of calls received25243Number of issues resolved14118Number of disputes settled001?The cost per minute of the resource supplied is $0.42.?On the Customer Cost Analysis report in time-driven activity-based costing, the time-driven activity rate for Resolving Problems would be closest to:

A. $1.50 per problem resolved
B. $11.76 per problem resolved
C. $28.00 per problem resolved
D. $0.42 per problem resolved


Answer: B

Business

You might also like to view...

Assume that you know the total dollar amount of a loan and the amount of the monthly payments. How can you determine the interest rate as a percentage of the loan?

Business

What kind of advertising would be found inĀ Florist, a magazine with a mission "to inform, inspire, and educate retail florists"?

Fill in the blank(s) with the appropriate word(s).

Business

Author Richard Laermer recommends that marketers avoid doing all of the following EXCEPT for

A) sending thank-you gifts to reporters. B) having colleagues handle media relations if they do not possess the connections. C) lying. D) ignoring small media outlets. E) meeting deadlines.

Business

Which of the following is the date that management commits itself to a formal plan to dispose of a business segment?

a. The measurement date b. The disposal date c. The assessment date d. The transfer date

Business