An item sells at a rate of 600 units per day. If a plant works two shifts per day (480 minutes each shift), what takt time is required for the plant to meet this demand?

What will be an ideal response?


480 minutes per shift × 2 shifts = 960 minutes per day
960 minutes per day ÷ 600 units = 1.6 minutes per unit, or 96 seconds per unit

Business

You might also like to view...

A "typical person" must believe the content of an advertisement to be false in order for the Wheeler-Lea Amendment to apply

Indicate whether the statement is true or false

Business

The capital account balances of a partnership are as follows: Trent, $50,000; Langston, $50,000; and Plank, $50,000 . If Felps pays $80,000 in cash to Plank to buy Plank's partnership interest, the entry on the partnership's books as a result of this transaction would include a

a. debit to Plank Capital, $80,000; b. credit to Felps Capital, $80,000; c. debit to Cash, $80,000; d. credit to Felps Capital, $50,000; e. debit to Cash, $50,000

Business

Which of the following is a reason is it risky for a coalition to remain intact after the successful resolution of an issue?

A. All of these are reasons it is risky for a coalition to remain intact after successful resolution of the issue. B. revenge of the vanquished C. desire for anonymity D. turmoil within

Business

In which stage of the product life cycle will promotional expenditures be significantly high in an attempt to create consumer awareness of a product and its features?

A) product development B) introduction C) growth D) maturity E) adoption

Business