Laddering tasks in a network diagram means

a. one task is completed then the next until the final task is complete.
b. each successive task is higher in cost than its predecessor task.
c. allows the project to be completed in the shortest possible time while making the best use of available resources.
d. the resources have to wait until the predecessor activity is complete to move to the next level in the work breakdown structure.


c

Business

You might also like to view...

An accounting system that maintains an adequate audit trail is implementing which internal control procedure?

a. access controls b. segregation of functions c. independent verification d. accounting records

Business

How are solutions initially presented in the team problem-solving process?

a. by a nominated leader of the group with input by the solution writer b. by each team member individually, followed by commentary after reading c. by each team member individually without comment from others d. anonymously, by a nominated leader

Business

Compare and describe group member behaviors from the first stage growth of a group (dependency and inclusion) to the early growth stages of human development of children.

What will be an ideal response?

Business

Secure wireless networks can be legally accessed by anyone and are frequently posted as such

Indicate whether the statement is true or false.

Business