Use this activity precedence table to create a resource loading profile. Activity lengths are given in days and an 8-hour day is assumed

Activity Time Predecessor
A 2
B 3 A
C 6 B
D 5 A
E 3 C
F 2 D
G 2 E,F

What will be an ideal response?


The loading chart is as follows:

Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A 8 8
B 8 8 8
C 8 8 8 8 8 8
D 8 8 8 8 8
E 8 8 8
F 8 8
G 8 8
Total 16 16 16 16 16 16 16 16 16 8 8 8 8 8 8 8

The loading profile shows the number of hours required for each of the 14 days of the project.

Business

You might also like to view...

Maturity value minus discount amount is called

a. the discount; b. proceeds; c. the principal; d. the maturity value; e. the rate.

Business

Magnolia Company has identified seven activities as part of its manufacturing process and chosen corresponding activity drivers for each activity. The chart below lists the total cost of each activity, the amount of activity driver used for each of Magnolia's two products, the activity rate, and the activity cost assigned to each product. Fill in the blanks below:ActivityCostActivity DriverDriver UsageActivity RateActivity Cost: Prod. 1Activity Cost: Prod. 2???Prod. 1Prod. 2???Design$60,000Design time800 hours1,200 hoursa.b.c.Preparation$18,000Labor hours3,000 hoursd.e.$9,000f.Machining$90,000Machine

hoursg.h.$18.00/hour$27,000i.Finishingj.Batches200300$50/batchk.l.Inspectionm.Unitsn.o.$6/unit$3,000$6,000Packagingp.Ordersq.50$300/order$13,500r.Shipping$17,000Packages70s.t.u.$3,000 What will be an ideal response?

Business

How should each team member end their speaking contribution in team huddle?

a. describing a problem that was solved b. suggesting a new course or strategy for the team c. describing a problem that still needs addressing d. giving a personal evaluation of another team member

Business

Prior period adjustments ________.

A. are shown on the statement of retained earnings as corrections to the beginning balance B. always increase the beginning balance of retained earnings C. must be recorded in the period in which the error occurred D. can be ignored because the financial statements have already been issued

Business