The critical path for the network activities shown below is ________ with duration ________

Activity Duration Immediate
Predecessors
A 4 ---
B 2 A
C 7 --
D 4 A
E 5 B,C,D

A) A-B-D; 10
B) A-B-E; 11
C) C-E; 12
D) A-D-E; 13
E) A-B-C-D-E; 22


D

Business

You might also like to view...

Audit Committee Responsibilities Describe the responsibilities of audit committees, and list at least four responsibilities that the NYSE has mandated for audit committees

Business

A management concept that seeks to uncover and eliminate waste in business activities is called:

A. Lean business model. B. Customer orientation. C. Just-in-time. D. Theory of constraints. E. Continuous operations.

Business

Which of the following is not a typical characteristic of a linear programming problem?

A) Restrictions exist. B) A choice among alternatives is required. C) The problem can be solved graphically. D) The problem has an objective.

Business

What is the purpose of a written code of ethics?

What will be an ideal response?

Business