The critical path for the network activities shown below is ________ with duration ________
Activity Duration Immediate
Predecessors
A 4 ---
B 2 A
C 7 --
D 4 A
E 5 B,C,D
A) A-B-D; 10
B) A-B-E; 11
C) C-E; 12
D) A-D-E; 13
E) A-B-C-D-E; 22
D