The delaying of any activity on the ________ will delay the completion of the project by the same amount.
Fill in the blank(s) with the appropriate word(s).
critical path
Critical path means the path(s) with the longest duration through the network. If an activity on the critical path is delayed, the project is delayed the same amount of time.