The delaying of any activity on the ________ will delay the completion of the project by the same amount.

Fill in the blank(s) with the appropriate word(s).


critical path

Critical path means the path(s) with the longest duration through the network. If an activity on the critical path is delayed, the project is delayed the same amount of time.

Business

You might also like to view...

______________________________, when applied to cash receipts, is the time between the payment by a customer and the availability of funds on deposit and available for use

Fill in the blank(s) with correct word

Business

The difference between the maturity value of the note and the bank discount is called the ____________________

Fill in the blank(s) with correct word

Business

What is a deed of trust?

What will be an ideal response?

Business

Reports written at the supervisor and managerial levels are more important than those written by employees at lower levels in the organization

Indicate whether the statement is true or false

Business