A project consists of seven independent tasks with processing times (in hours) given by 4, 5, 6, 7, 8, 9, and 12.Find the project finishing time Fin for N = 2 processors using the critical-path algorithm.
A. Fin = 26 hours
B. Fin = 21 hours
C. Fin = 25 hours
D. Fin = 27 hours
E. Fin = 28 hours
Answer: D
You might also like to view...
Provide an appropriate answer.Fill in the blanks (four of them) with the best responses:To use DeMoivre's theorem to find the n nth roots of a complex number: 1. Express the number in ________________form. 2. Express the root as a ________________ exponent. 3. Use n =
with ? to find one root. 4. Use
n =
and add _______° to ?, _________ times.
A. rectangular; decimal; 360; n - 1 B. fractional; polar; 360; n - 1 C. fractional; polar; 180; n - 1 D. polar; fractional; 360; n - 1
Solve the problem.The table lists blood types in a sample of hospital patients. Make a bar graph for the relative frequency data.
What will be an ideal response?
Use a graphing calculator to solve the equation. Round your answer to two decimal places.e2x = x + 3
A. {0.27} B. {3.27} C. {0.65} D. {3.65}
Complete the graph by shading the correct region.x - y ? 7
A.
B.
C.
D.