Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1?

1 2 3 4 5
Gross Requirements 400 500 300
Scheduled receipts 0 0 0 0 0
Projected ending Inventory 100 100
Net Requirements
Planned Receipts 300
Planned Orders

A) 200
B) 300
C) 400
D) 500


Answer: D

Business

You might also like to view...

In the BCG matrix, income from ________ can be used to help finance the company's question marks and stars

A) dogs B) cash cows C) SWOTs D) overseas operations E) low-share businesses

Business

Which of the following statements is false?

a. Normal losses which can be associated with a particular job, are charged (net of disposal)to that job. b. A job order cost system may produce both normal and abnormal losses. c. Normal losses, which can be anticipated, are included as a part of predetermined overhead. d. Abnormal losses are treated as product costs.

Business

The English philosopher John Locke viewed a newborn child as a "tabula rasa", or a(n) ________.

A. bundle of joy B. finished product C. blank tablet D. empty vessel

Business

Which of the following is true for collaborative relationships?

a. They involve very little effort. b. They require early supplier involvement. c. They are suitable for noncritical or one-time purchases. d. They are not intended for product innovation.

Business