On-site changes in the original design that are made during construction are documented in the _____.
a. as-built drawings
b. takeoff sheet
c. project schedule
d. job specifications
a. as-built drawings
You might also like to view...
When constructing wall panels for a platform-framed structure, the wall panels _____.
a. are built in position b. are always placed using a crane c. are all framed before the first panel is raised d. are assembled on the subfloor
A(n) __________ frame minimizes twisting of the steering neck by having the upper frame tubes at a wide angle to the neck.
A. single cradle B. backbone C. double cradle D. perimeter
In a tilt-up wall building, the wall panels are precast on a concrete slab-on-ground, which is the first floor slab of the building. In some buildings, the first floor of the building is not a concrete slab-on-ground but an elevated slab. Explain how the tilt-up walls are cast in this type of building.
What will be an ideal response?
The objectives of the presentation should be stated by the presenter at the outset
Indicate whether the statement is true or false