If the standard deviation is 6.5, the Z value is 1.5, and the expected date of completion is 15 weeks, then the due date for project completion is ______.
A. 24.75 weeks
B. 22.75 weeks
C. 29.75 weeks
D. 14.75 weeks
A. 24.75 weeks