A built-up wood girder is usually indicated by ____ and a note specifying the number of pieces of wood and their sizes.

A. a single solid line
B. a single dotted line
C. two or more lines
D. a circle


Answer: C

Trades & Technology

You might also like to view...

Explain the difference among (a) fine-grained soils and coarse-grained soils, (b) sand and gravel, and (c) silt and clay.

What will be an ideal response?

Trades & Technology

Sketch in cross section: (a) CFS stud section, (b) CFS track section, (c) CFS hat section, and (d) CFS Z section.

What will be an ideal response?

Trades & Technology

Which of the following is NOT a preplant fertilizing method?

a. Broadcasting b. Topdressing c. Soil injection

Trades & Technology

The layers of contrasting material found when one digs a hole in the ground are called ________

A) pedons B) soil structure C) regoliths D) pseudoliths E) horizons

Trades & Technology