If a project is expected to be completed in 68 days with a project variance of 21 days, what is the probability that the project will be completed within 50 days?
a. less than 1%
b. between 5% and 10%
c. between 15% and 30%
d. over 35%
a. less than 1%
You might also like to view...
The informal communication processes within the organization, including stories, jokes, and gossip, constitute which of the following?
A. retention B. equifinality C. cultural network D. synergy
_____ occurs when the gap between pay for newcomers and veteran employees narrows because of changing economic conditions over time.
A. Pay depression B. Wage compression C. Leveling D. Econometric distribution E. Equalization
Which of the following is true of a mediator?
A) A mediator should arrive at a final decision. B) A mediator can be obtained from the local bar association. C) A person who does not have a background in law is generally preferred as a mediator. D) If the mediator is not from a governmental organization, the agreement signed during mediation is not valid.
Dagostino Corporation uses a job-order costing system. The following data relate to the just completed month's operations.(1) Direct materials requisitioned for use in production, $154,000(2) Indirect materials requisitioned for use in production, $45,000(3) Direct labor wages incurred, $94,000(4) Indirect labor wages incurred, $119,000(5) Depreciation recorded on factory equipment, $44,000(6) Additional manufacturing overhead costs incurred, $83,000(7) Manufacturing overhead costs applied to jobs, $236,000(8) Cost of jobs completed and transferred from Work in Process to Finished Goods, $458,000Use the following T-accounts to answer the following questionsWork In ProcessBal.$48,000 Manufacturing
Overhead The total amount of manufacturing overhead actually incurred was: A. $236,000 B. $291,000 C. $247,000 D. $246,000