Each balloon needs to have its own leader line to avoid confusion.
Answer the following statement true (T) or false (F)
False
You might also like to view...
Architect’s Supplemental Instructions (ASIs) should not be used to change the _____ or contract time.
a. specifications b. correspondence c. document log d. contract sum
Vertical slipforming is used primarily for structures with a height greater than _____.
a. 100 feet b. 80 feet c. 50 feet d. 40 feet
Además del NEC®, la energía eléctrica de emergencia para hospitales es regida por la:
a. National Hospital Association (Asociación Nacional de Hospitales). b. Joint Commission (Comisión Conjunta). c. American Medical Association (Asociación Médica Estadounidense). d. Medicare Commission (Comisión de Medicare).
The letters ____ are included on the drawing specifications to indicate when a left-hand thread is required.
A. LH B. LHT C. LT D. LTH