Two people developed first-cut cost estimates to construct a new 130,000 square foot building on a university campus. Person A applied a general-purpose per unit cost estimate of $180 per square foot for the estimate. Individual B was more specific: she used the area estimates and per unit cost factors shown below. (a) What are the cost estimates developed by the two people? (b) What is the percent increase between the lower and higher cost estimates?
You might also like to view...
How much material is to be removed from Item 2 during the machining process?
Refer to Drawing Number 09022601 REV D.
The pH of a poinsettia's soilless media should be _____
A) 5.8-6.2 B) 5.0-6.4 C) 6.0-6.4 D) 6.4-7.0
The Marshall and Swift (M&S) equipment cost index started with a base value of 100 in 1926. Determine the average (compound) percentage increase per year between 1926 and 2011 when the index value was 1490.2.
What will be an ideal response?
A clutch is being removed to gain access to replace a leaking block expansion plug. Technician A says that the pressure plate should be marked so it can be reinstalled in the same location on the flywheel just in case the vehicle uses a? clutch/flywheel that is balanced as an assembly. Technician B says that the clutch disc should be marked so it can be installed on the input shaft in the same location. Which technician is? correct?
A. Technician A B. Neither Technician A nor B C. Technician B D. Both Technicians A and B