What is the slack time for activity H?
Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.
Activity Predecessor Duration Early Start Early Finish Late Start Late Finish
A - 10
B - 7 11
C A 7
D A 15 14
E B 11 19
F B 10
G D,E 24
H F 24
J C 28
K G,H,J 36
A) 1
B) 2
C) 3
D) 4
Answer: D
You might also like to view...
______ refers to the notion that communication requires the involvement of others.
a. “Communication involves messages” b. “Communication is collaborative” c. “Communication is participatory” d. “Communication is a process”
The efficiency of a factory is 75% and its utilization 50%. If effective capacity is 1000 find design capacity
What will be an ideal response?
Those who knowingly violate the Clean Air Act are exempt from criminal penalties
a. True b. False Indicate whether the statement is true or false
The Revised Act provides that only one person need act as the incorporator, though more may do so
Indicate whether the statement is true or false