Item A has a lead time of 2 weeks and requires two units of Item B and three units of Item C. Item B has a lead time of 4 weeks; Item C has a lead time of 1 week. What should the planning horizon of the MRP be?
a. 2 weeks
b. at least 6 weeks
c. always less than 6 weeks
d. 3 weeks
b. at least 6 weeks
You might also like to view...
Qualifying dimensions, in contrast with determining dimensions,
A. are the customer-related dimensions in a product-market. B. indicate whether a person might be a potential customer but do not show which product or brand that person might buy. C. affect the product or brand a person is likely to purchase. D. are the only kind of dimensions useful for marketing strategy planning. E. None of these answers is correct.
The managerial function of ____________________ is concerned with making certain that plans are correctly implemented and are being achieved.
Fill in the blank(s) with the appropriate word(s).
Which of the following employees would NOT be covered under OSHA guidelines?
a. a worker working in a coal mine b. a worker working in a nuclear power plant c. a federal office worker d. a secretary in a law firm e. a grocery store employee
________ striving reflects a strong desire to obtain power and influence within a social structure as a means of expressing personality.
A. Communion B. Accomplishment C. Fellowship D. Attainment E. Status