If a project is expected to be completed in 68 days with a project variance of 9 days, what is the probability that the project will be completed within 50 days?
A. 0%
B. between 5% and 10%
C. between 15% and 30%
D. over 35%
A. 0%
You might also like to view...
A merchandiser uses a perpetual inventory system. The beginning Retained Earnings balance of the merchandiser was $110,000. During the year, Sales Revenue amounted to $90,000, Cost of Goods Sold was $40,000, and all other expenses totaled $12,000. The company declared and paid $27,000 as dividends. The ending balance of Retained Earnings would be ________.
A) $148,000 B) $121,000 C) $175,000 D) $110,000
Which item below states that behavior is a function of its consequences and is determined exclusively by environmental factors, such as external stimuli and other reinforcers?
A. operant conditioning B. conditioned response C. reinforcement theory D. classical conditioning
There were several leftover cookies in my lunchbox
A) there; were B) cookies; were C) lunchbox; were D) cookies; were leftover
A special assessment tax is:
A. A waiver of property taxes for businesses willing to locate within a government's jurisdiction. B. Assessed only against certain property owners who are deemed to benefit from the service or project being paid for by the proceeds of the special assessment levy. C. Assessed against all property owners following a referendum in which voters approved the special project being constructed. D. None of the above.