Which of the following correctly calculates an activity's cost slope?
A. (normal time - crash time)/(crash cost - normal cost)
B. (normal time - crash time)/(normal cost - crash cost)
C. (crash cost - normal cost)/(normal time - crash time)
D. (normal cost - crash cost)/(normal time - crash time)
E. (crash cost - normal cost)/(crash time - normal time)
Answer: C
You might also like to view...
The confidence factor for nonstatistical sampling is based on:
A. the number of items in the account. B. auditor judgment. C. variability in the population and the risk of misstatement in the account. D. the risk of misstatement in the account and the level of desired confidence.
When using univariate techniques, the number of samples is determined based on how the data are treated for the purpose of analysis, not based on how the data were collected
Indicate whether the statement is true or false
While the concept of knowledge management is seen as novel and innovative, its practice of transforming employees’ tacit knowledge into explicit knowledge owned by the company was the driving force behind the ideas of ______________.
a. Elton Mayo b. Max Weber c. Fredrick Taylor d. Mary Joe Hatch
Which of the following terms denotes the defendant's written response to a plaintiff's complaint that is filed with the court and served on the plaintiff?
A) summons B) answer C) rejoinder D) rebuttal