The amount of time an activity can be delayed and yet not delay the project is termed
A. Free slack.
B. Critical float.
C. Float pad.
D. Total slack.
E. Slip pad.
Answer: D
You might also like to view...
Answer the following statements true (T) or false (F)
1. A partnership is a business with two or more owners that is legally organized as a corporation. 2. The articles of partnership is a written contract between partners that specifies the name, location, and nature of the business; the duties of each partner; and the method of sharing profits and losses among the partners. 3. A written partnership agreement is also known as the articles of partnership. 4. The addition of a new partner to a firm does not dissolve the old partnership. 5. Mutual agency means that any partner can legally bind the other partners and the partnership to business contracts within the scope of the business's regular operations.
A lessee under a consumer lease and a buyer under a sale of goods are provided with the same protections against unconscionability under the UCC
a. True b. False Indicate whether the statement is true or false
Compared to the other promotion mix tools, personal selling offers the marketer the greatest control over the situation.
Answer the following statement true (T) or false (F)
All of following are true of learning curves EXCEPT:
a. they are not used for a pricing strategy. b. they are affected by the ratio of manual to machine work. c. 80 percent learning curves exhibit a step initial decline and then level off. d. they are used in defense industries.