It is possible for a project network to have more than one critical path.
Answer the following statement true (T) or false (F)
True
Critical path means the path(s) with the longest duration through the network. If an activity on the critical path is delayed, the project is delayed the same amount of time. A network may have multiple critical activities resulting in multiple critical paths.
You might also like to view...
A patent is amortized over its expected useful life or 20 years. The expected useful life can be impacted by all of the following except
A) a unsuccessful lawsuit against a competitor. B) the federal government renewing the original patent. C) technical innovations by a competitor. D) product improvements by the patent holder.
Which of the following controls would be most successful in mitigating the theft of customer checks received in the mail?
a. Custody of receipts by the accounts receivable manager. b. Restricted endorsements placed on the check as soon as it arrives. c. Weekly deposits to a secure bank. d. Reconciliation of bank accounts each month.
The first step in the development of a retention schedule is to
A. Classify the records. B. Determine the necessity for records. C. Conduct a records inventory. D. Assess the suitability of the storage equipment.
Harvey Hadley conveyed a parcel of property in the city of Fairlywell Downs to Carl Bland and Dirk Pitts. The granting clause of the deed stated that Carl and Dirk take the property jointly. Neither Carl nor Dirk signed the deed. a . What is the nature
of the joint ownership interest of Carl and Dirk? Explain? b. Of what impact is it that neither Carl nor Dirk signed the deed? Explain? c. If the property were still in escrow, of what effect would a recorded tax lien be?