A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes

After line balancing, the largest possible assigned cycle time is ________ minutes, and the smallest possible assigned cycle time is ________ minutes.
A) 1.8; 1.4
B) 1.6; 0.9
C) 6.4; 2.4
D) 2.4; 0.9
E) 6.4; 0.9


C

Business

You might also like to view...

When might one choose to use each kind of the three message design logic responses?

What will be an ideal response?

Business

The acquisition cost for nonmonetary assets includes

a. invoice price, only. b. invoice price and transportation costs, only. c. invoice price, transportation costs, and installation costs, only. d. invoice price, transportation costs, installation costs, and handling charges, only. e. invoice price, transportation costs, installation costs, handling charges, and first year's maintenance cost.

Business

The following explains contribution margin ________.

A. sales minus fixed cost B. fixed cost minus variable cost C. sales minus variable cost minus fixed cost D. sales minus variable cost

Business

A variable cost increases in total and per-unit when output increases

Indicate whether the statement is true or false

Business