The pieces of equipment required to place 160 cubic yards of concrete in 1 day by experienced workmen are two gasoline engine vibrators and one concrete pump. If the vibrators cost $76 per day and the con­crete pump costs $580 per day, the variable cost of the equipment per cubic yard of concrete is closest to: (choose one)

(a) $0.95
(b) $3.63
(c) $4.10
(d ) $4.60


Cost/yd³ = [2(76) + 580]/160 = $4.58

Answer is (d) $4.60

Trades & Technology

You might also like to view...

An incandescent light uses an electric current to heat a(n) ____________________ wire to a high temperature until it glows or incandesces.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

What is Navistar International's current generation of interactive troubleshooting software known as?

A. Electronic Technician (ET) B. InSite C. ServiceMaxx (SM) D. DAVIE

Trades & Technology

An op-amp has a +3 V on its inverting input and a +5 V on its non-inverting input. The output voltage is

A) +5 V B) +2 V C) -3 V D) -2 V

Trades & Technology

Refer to the figure. Determine rise, or offset

Fill in the blank(s) with the appropriate word(s).

Trades & Technology