Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 12, its other successor, Task E, has a latest start on day 12, and the duration of Task D is 2 days

a. day 14
b. day 10
c. day 12
d. cannot be calculated based upon information given.


b

Business

You might also like to view...

The accounts receivable method to estimate bad debts obtains the estimated balance in the Allowance for Doubtful Accounts in one of two ways: (1) computing the percent uncollectible from the total accounts receivable or (2) aging accounts receivable.

Answer the following statement true (T) or false (F)

Business

Briefly describe the three sets of collaboration tools.

What will be an ideal response?

Business

Consider the above Income Statement for CharmCorp. All values are in millions of dollars. If CharmCorp. has 4 million shares outstanding, and its managers and employees have stock options for 2 million shares, what is its diluted EPS in 2008?

Income Statement for CharmCorp: 2008 2009 Total sales 600 540 Cost of sales -532 -488 Gross Profit 68 52 Selling, general, and administrative expenses -36 -21 Research and development -4 -5 Depreciation and amortization -5 -5 Operating Income 23 21 Other income 1 5 Earnings before interest and taxes (EBIT) 24 26 Interest income (expense) -7 -7 Pretax income 14 19 Taxes -4 5 Net Income 10 14 A) $0.83 B) $1.33 C) $1.67 D) $2.00

Business

A company can classify a debt security as held-to-maturity if it has the positive intent to hold the securities to maturity

a. true b. false

Business