The management of a factory finds that the maximum number of units a worker can produce in a day is 30. The learning curve for the number of units N produced per day after a new employee has worked days is modeled by
. After 20 days on the job, a worker is producing 19 units in a day. How many days should pass before this worker is producing 25 units per day?
?
A. about 36 days.
B. about 45 days.
C. about 30 days.
D. about 10 days.
Answer: A
Mathematics
You might also like to view...
Find an equation of variation in which the following are true.x varies inversely as y2, and x = 15 when y = 14.
A. x = 2940y2
B. x =
C. x =
D. x =
Mathematics
Solve the triangle, if possible. Approximate values to the nearest tenth when appropriate.? = 30°, a = 19.40, b = 38.8
A. ? = 60°, ? = 90°, c = 33.6 B. ? = 60°, ? = 60°, c = 33.6 C. ? = 90°, ? = 60°, c = 33.6 D. No solution
Mathematics
Multiply.0.0606 × 4.04
A. 0.254824 B. 0.26664 C. 0.27664 D. 0.244824
Mathematics
Find the indicated term of the sequence.The twelfth term of the arithmetic sequence -13, -9, -5, ...
A. -61 B. 31 C. -57 D. 35
Mathematics