A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3, a complexity risk of 0.7, and a dependency risk of 0.8. The probability of failure is:

A) Less than or equal to 0.3.
B) Greater than 0.3 but less than or equal to 0.55.
C) Greater than 0.56 but less than or equal to 0.89.
D) Greater than or equal to 0.9.


C

Business

You might also like to view...

Suppose you're a manager who has to write performance reviews. What can you do to help you prepare for writing a review that includes negative information?

What will be an ideal response?

Business

During the early phases of leadership making, leaders look for what qualities in followers?

A. agreeableness and cooperation B. good humor and intelligence C. enthusiasm and participation D. pleasantness and trustworthiness

Business

What did the Print Tradition offer that the Written Tradition did not?

a. an alphabet b. distribution of printed text c. localization of literacy d. geographic limitations

Business

The Worker Adjustment and Retraining Notification (WARN) Act is a federal act that requires employers with 100 or more employees to give their employees 60 days' notice before engaging in certain plant closings or layoffs

Indicate whether the statement is true or false

Business